The desirability of having higher energy heavy ion beams for experiments
in the areas of nuclear and atomic physics is by now well established. A few
heavy ion boosters are already in operation at some laboratories. Most of these
boosters are based on the technique of radio-frequency acceleration using
cavity resonators made of both normal and superconducting materials. For the Pelletron at
The quarter wave resonators operating at 150 MHz are made of OFHC
copper. A schematic drawing of a QWR is shown in Fig. The tapered inner
conductor and the cylindrical outer wall are connected together by the base plate
which is e-beam welded to these parts. The base plate to the outer wall has a
deep penetration weld from the outer side and a cosmetic one from the inside.
This cosmetic weld has been the most difficult operation in the fabrication of
the cavities. The machining and the e-beam welding of the cavities are done at
the central workshop, BARC. The two drift tubes on the outer can are hydrogen
brazed into position after adjusting the cavities to the designed
frequency. Since Pb
is the superconducting element in the design of our cavities, the resonators
made of OFHC cooper have to be coated with a thin layer of Pb
~ 2 mm, on the inner surface. The performance of the cavity largely depends on
the surface qualities of this Pb layer. A lot of care
is thus taken in the preparation of the cavity surface prior to the lead
plating.
First, the resonator is subjected to a sequence of mechanical
polishing with fine abrasives of various grades using a tumbling machine. The
final tumbling is done using walnut shells. A submicron surface finish is
achieved by the mechanical polishing. The next stage of surface preparation
involves electropolishing in a chemical bath of orthophosphoric acid, alcohol and water maintained at a
temperature less than 180 C. After electropolishing,
the resonator is washed, wetted and etched mildly with dilute citric acid. The
resonator is then washed with de-ionized water and the lead fluoborate
plating solution is poured into it as quickly as possible. All these operations
are done in a specially designed covered sink with air flow controls. The lead
deposition is done using pulsed electroplating at a current density of about
0.7 mA/cm2 The plating is done for a
specified time to obtain 2 mm thick Pb coating. The
plated Pb layer is thoroughly washed with high
quality DI water, passivated with EDTA and dried with
flowing Ar gas. The dried resonator is stored in
vacuum.
The performance of the resonator is evaluated by measuring, in the
superconducting state, its quality factor Q as a function of the electric field
developed in the cavity. These measurements are done in a liquid helium
cryostat developed in-house. This cryostat can hold one resonator and has all
the connections and controls needed to measure the cavity Q as a function of
the electric field. RF power to the cavity is coupled through an inductive loop
which can be driven in and out of the cavity remotely by a stepper motor. After
proper bake out of the resonator, it is cooled to liquid helium temperature. In
the superconducting state, to measure Q at different field levels, the cavity
is pulse powered under critical coupling at various field values as measured
from the cavity pick up probe. The decay of the stored energy $U$ in the cavity
is then observed to measure the characteristic decay time $\tau$
of the cavity given by
U=Uo
/exp (-t/t)
The
quality factor Q=wt, where w is the resonant frequency. This procedure to
measure Q is good at relatively low field levels. A typical decay time for the
QWR measured in our laboratory is about 180 msec. At
high field levels, since the loss mechanisms are not purely resistive, Q is
calculated from the measured input RF power in CW mode using the relation
Q= wU/P
where P is the
measured input power and U is the stored energy for the given Eacc. The Q vs Eacc curve for a QWR measured in our
laboratory is shown in Fig.4 before and after helium conditioning[4].
At a power dissipation of about 7 watts, it has been possible to run the cavity
in CW mode at a field of 2.8 MV/m without any serious problems. Two resonators
built indigenously have been tested so far and three more are under different
stages of testing. As mentioned earlier the most difficult problem for us so
far has been the cosmetic e-beam weld between the end plate and the outer can; even
a slight porosity in this weld causes improper lead film deposition resulting
in poor Q values.
The modular liquid helium cryostat is designed to hold four b=0.1 QWRs. The various resonator and cryogenic parameters are
controlled and monitored from outside using UHV compatible vacuum feed throughs. The liquid helium storage tank to which the four
resonators are attached has a liquid helium holding capacity of 45 litres. The
resonators are cooled by liquid helium through gravity flow. Both the helium tank
and the resonators are surrounded by liquid nitrogen shields maintained at 77K.
A few layers of high quality aluminized mylar
wrappings on the nitrogen shields provide partial thermal insulation at 77K.
The static heat load at 4.2K of this cryostat with all attachments is about 2
watts.
1.
M.B. Kurup, R.G. Pillay and H.G. Devare, Indian J. Phys. 62A, 706 (1988).
2.
R.G. Pillay, M.B. Kurup, A.K. Jain, D.
Biswas, S.A. Kori and B. Srinivasan, Indian J. Pure and Appl.
Phy. 27, 671 (1989).
3.
B. Srinivasan, Animesh Jain, S.A. Kori and R.G. Pillay, DAE Symp. Nucl. Phys. 32B,
(1989).
4.
B. Srinivasan, DAE Symp. Nucl. Phys. 36A, 157 (1993).